Kouklia, Pafos
Duration:2008-2010
Client:SIEMENS (MAIN CONTRACTOR)
Work Description:33kV/132kV SUBSTATION ERRECTION
> MV (33kV) Switchgears Installation > MV (33kV) Power Cables Laying and Termination > Erection of 132kV Switchyard 132kV substation Main 2MVA 132/33kV Transformer and assosiated equipment > Erection of Main 132/33kV Transformer and Assosiated equipment > Earthing system > Small power, Lighting and Security Systems for Substation and Control rooms